Posted by: iMalqata Blog | January 13, 2016

Preserving the Architecture of the King’s Palace Continues

Tony Crosby

Although the actual preservation program this season will be relatively short, we have several very important issues to address. In the January 10th blog the two primary purposes of preservation and presentation were discussed and defined as actually preserving the remains in such a way that they are also understandable to the public once the site is open and accessible. In previous seasons our first priority was insuring that the walls and wall fragments were protected in the main Palace area. While that basic approach continues, we are also concentrating on reconstructing several walls where little remains of the original and nothing remains above the present ground level.

Tony_Blog_1

Overall view of the west side of the main palace where we are currently working.

The reconstruction of these walls in the west side of the main palace will complete most of the basic “footprint” of this important section.

Work began this season by completing the west perimeter wall, which defines the extension of room suite to the west before completing the majority of the footprint for the west side. Several sections of this wall had been preserved in past seasons and our first priority was completing that feature. We have now moved into a section of this west suite of rooms, adding known features, reconstructing missing walls, and modifying details as more information becomes known, and repointing existing masonry. Our goal is to complete all of this work over the next several days and move on to the next priority of completing the south perimeter wall and preserving the wall of the east side of the main courtyard. In the process we will lay approximately 6,000 to 8,000 mud bricks and repoint approximately 200 meters of walls.

Tony_Blog_2

Workmen reconstructing a portion of a wall to complete the “footprint” of this area. 1910-11 Met site plan in foreground.

We will not be working this season in the section of the Palace that contains Amenhotep III’s private chambers as conservation of the more extensive wall painting in that area has to be undertaken first. These areas are currently protected until that more extensive painting conservation work can be undertaken.

We continue to plan future preservation work for the two purposes described above by cleaning, mapping and documenting construction details such as brick sizes and coursing patterns and prioritizing the specific walls and areas by condition, conservation needs and interpretive significance.

January 13, 2016

Advertisements

Responses

  1. Looking forward to future blogs about this interesting site!

  2. […] the Architecture of the King’s Palace Continueshttps://imalqata.wordpress.com/2016/01/13/preserving-the-architecture-of-the-kings-palace-continues/Close Encounters with an […]


Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Categories

%d bloggers like this: